Horizontal & vertical curves
Roads and pipes change direction with circular arcs in plan and parabolas in profile. A handful of formulas cover most design and staking questions.
Horizontal (circular) curves
Two tangents meet at the PI with an intersection angle Δ (the change in direction). A circular arc of radius R joins them, starting at the PC and ending at the PT. The central angle of the arc equals Δ.
E = R(sec(Δ/2) − 1) M = R(1 − cos(Δ/2))
T is PI to PC (and PI to PT), L is the arc length, LC the long chord PC–PT, E the external distance from the PI to the curve midpoint, and M the middle ordinate from the chord midpoint to the curve.
Degree of curve
US highway practice describes sharpness by the angle subtended by a 100-ft arc: D = 5729.58/R (the "arc definition"). A 5° curve has R ≈ 1,146 ft. Older railroad work uses a 100-ft chord instead, which gives slightly different numbers.
Stationing through a curve
PC = PI − T, then PT = PC + L. A common mistake is PT = PI + T. Stations run along the curve, and the arc L is shorter than the two tangents (2T), so PI + T overstates every station beyond the curve.
Staking by deflection angles
From the PC, the angle between the back tangent and the chord to any point on the curve is half the central angle to that point: δ = Δ·l/(2L) for arc length l. At the PT it equals Δ/2. Each stake is set by turning δ and measuring the chord 2R·sin δ from the PC (or the sub-chord from the previous stake).
Vertical curves
In profile, grade g₁ meets grade g₂ at the PVI. An equal-tangent parabola of horizontal length L runs from the PVC (L/2 before the PVI) to the PVT (L/2 after). The parabola changes grade at a constant rate, which is why it is used: equal steps give equal changes in grade.
With grades in percent use g₁·x/100 and A·x²/(200L). A negative A is a crest, positive a sag.
High and low points
The grade along the curve is g₁ + (A/L)·x. It is zero at x = −g₁·L/A. If that lands between 0 and L the curve has a high (crest) or low (sag) point there — the place to put a sag inlet or check cover over a pipe. If it doesn't, the extreme is at the PVC or PVT.
The middle ordinate
The curve passes A·L/800 (grades in %, L in ft) above or below the PVI. Example: g₁ = +2 %, g₂ = −1.5 %, L = 400 ft → A = −3.5, so the curve is 1.75 ft below the PVI.
K value
K is the horizontal distance needed for a 1 % change in grade. Design manuals (AASHTO Green Book, Caltrans HDM, local standards) set minimum K for stopping sight distance on crests and headlight distance on sags. The vertical-curve tool reports K; compare it with the governing table for your design speed.
Try it in the calculators
- Open the calculator: Horizontal curveTry an exampleSimple curve, chord definition: PI 18+00, I = 45°, D = 15°
- Open the calculator: Vertical curveTry an exampleSummit curve G1 +3.2 %, G2 −1.6 %, L 400 ft, PVI 14+00 elev 131.20
When not to use: this guide teaches the method. It is not a survey standard and does not replace your state's minimum technical standards for surveys or the project specifications.
Original explanations written for this site. Plane-surveying fundamentals only — not exam questions, and not a substitute for a surveying text or your agency's survey manual.