Units, distances & stationing

Surveying numbers look simple, but three small things trip people up: which foot, which distance, and how stations are written.

Which foot?

There have been two "feet" in US surveying. The international foot is exactly 0.3048 m. The US survey foot is 1200/3937 m, about 0.3048006 m. The difference is two parts per million — invisible on a lot, but about 2 ft on a state-plane northing of a million feet. NIST and NOAA retired the US survey foot for new work at the end of 2022, but many existing maps, plans and control sheets still use it.

Practical rule: read the basis of coordinates note on the plans or record map, and never mix coordinates from two sources until you know both use the same datum, zone and foot.

Horizontal, slope and vertical distance

Coordinates, stations and areas are all built on horizontal distance. A total station or tape measured along the ground gives slope distance S. With the zenith angle z (0° straight up, 90° level) or the height difference Δh:

H = S · sin z    V = S · cos z    H = √(S² − Δh²)

Example: S = 250.00 ft and the far point is 12.0 ft lower. H = √(250² − 12²) = 249.71 ft. Using the slope distance by mistake puts every later point 0.29 ft too far out.

Grid and ground

State-plane coordinates live on a projection. Distances on the grid differ from ground distances by a combined factor (grid scale factor × elevation factor), typically differing from 1.0 by a few parts per 100,000 up to several parts per 10,000 in California, depending on zone position and elevation. For a site this tool set assumes a local plane grid — if your control is state plane, ask the surveyor whether the plans are on grid or ground and apply the factor once, consistently.

Stationing

A station is a distance along an alignment written as hundreds "+" remainder. 12+34.56 means 1,234.56 ft from station 0+00. Adding is ordinary arithmetic: 12+34.56 + 287.45 = 15+22.01. Stations increase in the direction of the alignment; offsets are measured perpendicular to it, left or right looking up-station.

Grade and slope notation

Grade is rise over run. A 2 % grade rises 2 ft per 100 ft. Earthwork slopes on civil plans are usually written horizontal : vertical, so a 2:1 slope is 50 % and a 4:1 slope is 25 %. Angles are rarely used for design grades but show up in survey reductions: 2 % ≈ 1°08′45″.

Try it in the calculators

When not to use: this guide teaches the method. It is not a survey standard and does not replace your state's minimum technical standards for surveys or the project specifications.

Original explanations written for this site. Plane-surveying fundamentals only — not exam questions, and not a substitute for a surveying text or your agency's survey manual.